City of Cornwall
Water Main CIPP Relining

 

Timeframe/Results                         

  • 2005 construction season
  • Rapid five week completion period

 

Project Elements             

  • Installation, maintenance and removal of a temporary water system serving 75 residents
  • Complete relining of 1,200 linear metres of 150 mm diameter water main
  • Hydrant and valve replacement throughout

 

Feedback

  • CWW's responsive five-week project completion through the application of structural water main relining was highly beneficial to the City of Cornwall’s water main infrastructure

  • Direct project costs were significantly reduced, including the associated cost savings inherent to rehabilitating 1,200 linear metres of water main by structural relining vs. conventional dig and replace methods