City of Cornwall
Water Main CIPP Relining
Timeframe/Results
- 2005 construction season
- Rapid five week completion period
Project Elements
- Installation, maintenance and removal of a temporary water system serving 75 residents
- Complete relining of 1,200 linear metres of 150 mm diameter water main
- Hydrant and valve replacement throughout
Feedback
- CWW's responsive five-week project completion through the application of structural water main relining was highly beneficial to the City of Cornwall’s water main infrastructure
- Direct project costs were significantly reduced, including the associated cost savings inherent to rehabilitating 1,200 linear metres of water main by structural relining vs. conventional dig and replace methods