City of Ottawa:
Water Main Cleaning and Lining Program

 

Timeframe/Results         

  • 2005 construction season
  • Project implemented in year three of the City of Ottawa’s water main rehabilitation plan
  • Successful installation of Aqua Pipe™ structural liner and project completion on schedule and under budget 

 

Feedback                           

  • CWW’s structural relining methodology was favoured over open cut pipe replacement
  • Neighbourhood streets remained useable throughout project
  • Significantly shorter timeframe than conventional dig and replace methods

 

Project Elements             

  • Installation, maintenance and removal of a temporary water system serving 350 residents in three separate neighbourhoods
  • Complete relining of 5,490 linear metres of water main ranging in size from 150 mm to 300 mm
  • Hydrant and valve replacement throughout


Neighbourhoods            

  • Water mains were rehabilitated in the following locations:
    • The Heron Park neighbourhood in Ottawa between Clover Street and Falcon Street south of Heron Road and north of Brookfield Street
    • Grey Nuns Drive in Orleans between Jeanne d’Arc Boulevard and St. Joseph Boulevard
    • Orient Park Drive in Orleans between Innes Road to 1,100 metres south